How to see planned orders for P3 mrp type products in APO?

Former Member
0 Kudos

Dear experts,

I have materials with P3 MRP type (not planned in APO but in R/3 using MRP)

I have active integration models with P3 and X0 mrp type products for planned orders

however I can not see in APO product view the planned orders for P3 materials,

is this normal or should I see those planned orders in APO?

Thanks for your answer,

best regards

Elynn

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Elynn,

As per std, XO is the typical MRP type that should be used to display and

plan for a material in APO.

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Thank you for your answer

however what I don't understand is why I the purchase requisitions, purchase orders, dependent demand are CIFed (and visible in product view) for those materials with P3 MRP type whereas the planned orders created by MRP in R/3 are not CIFed.

Do you have any idea?

Thanks

E

Former Member
0 Kudos

Hi E

can you please check if these materials are present in the active planned order integration model?

Rgds, Sandeep

Former Member
0 Kudos

Hello,

Yes the integration models are correctly set up.

actually PldOrd STPO are not transferred to APO for products with MRP type P3 and procurement type F whereas PldOrd Stk are well transferred to APO for products with MRP type P3 (copy of P3) and procurement type E.

How can we get the PldOrd STPO (planned order with external procurement) correctly transferred to APO?

Thanks for you have any ideas...

kinds regards

E

Former Member
0 Kudos

Hi,

The following prerequisites must be met so that planned orders can be transferred from SAP R/3 to SAP APO

and vice versa:

1.The material masters must be transferred to SAP APO.

2. PPMs must exist for planning in SAP APO.

3. The relevant integration models must be active.

4. An active integration model for planned orders must exist in SAP R/3.

5.An active integration model must also exist for materials, so that the components of the planned order are transferred.

6.The relevant distribution definitions must be maintained in SAP APO, so that planning results can be

transferred from SAP APO to SAP R/3.

Thanks,

nandha

Former Member
0 Kudos

Hello,

The reason why the orders were not transferred to APO was due to Procurement type: It is not possible to integrate planned orders with external procurement into APO (order type STPO) and it's a standard system behaviour

Thanks