Former Member
0 Kudos

Dear all,

When we would like to activate the option u201CChanging destination at a tasku201D in SAP-TRM RF screens in order to be able to target a new bin address in a rack (and not a pick-up and drop-off node):

1. Do we have to set the indicator u201CDestination bin change during confirmation: 1 Storage bin can be changed during confirmationu201D at the target storage type level in SAP-WM Customizing of storage type definition (Warehouse Management -> Master Data -> Define Storage Type)?

2. Do we have to set the indicator u201CDest.stor.bin changeable during confirmation: 1 Storage bin can be changed during confirmationu201D at the target storage type level in SAP-WM Customizing of confirmation control entry (Warehouse Management -> Activities -> Confirmation -> Confirmation control for Storage type)?

Thx a lot in advance for your inputs

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Both options are same! check any entry

former_member1245242
Contributor
0 Kudos

Hi

we can set confirmation at many levels:-

1. Define storage type screen

2. Confirmation at Wh No - OMLX tcode

3. Confirmation at stor type - OMLX tcode

4. confirmation control at mov type - OMLX tcode