on 09-10-2010 7:21 PM
Hi,
We are implementing SAP SCM 5.0 integrated to SAP R/3 Mills IS.
During the execution of CFM2 transaction, while trying to activate the integration model for the object u201COrdersu201D for the very first time, the following error message appears:
*"Multi-level error propagation carried out".*
There are also messages related to inbound queues blocked. In the case of maintenance orders, CIF_MNT_INBOUND message shows up. While working with Production orders, CIF_ORDER_INBOUND message emerges.
The items listed below should be taken into account:
-The production orders that are meant to be transferred to APO are regular production orders corresponding to several products.
-We are working with configurable materials.
-We are working with the active model (000) and for each plant we are using 2 different planning versions.
Regards,
Analía Nahmías
Dear Analía,
The corresponding error messages issued when executing //CCR indiacted the peg-ids are missing in liveCache.
Recommendations:
-Run transaction /SAPAPO/OM17 to check the internal consistency between database and liveCache within SCM system. Correct the inconsistencies
-Execute report /sapapo/cif_deltareport3 to correct the inconsistencies between ECC and SCM system
Regards,
Tibor
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.