First step in network planning with SNP

Former Member
0 Kudos

Hi

May I know the first step in network planning with SNP from the following:

1. first step is procurement planning

2. first step is production planning

3. first step is deployment

4. first step is distribution via stock transfers

Thanks in advance

Accepted Solutions (1)

Accepted Solutions (1)

somnath_manna
Active Contributor
0 Kudos

First step would be master data setup.

Assuming that is done, then run

1. SNP Low Level Code

2. Run Location by Location Heuristics or Network Heuristic for Finished products (will create STRs / Purchase Reqs)

3. Run PPDS Planning Run or SNP Location Heuristic (depending on material requirement and horizon) to create In-house Production and External Procurement Order

4. Carry out execution steps for completion of Production and Purchase Orders

5. Carry out Deployment and TLB to distribute finished products to demand points of the supply chain (where Location Heuristic was first executed)

Hope this helps.

Somnath

Former Member
0 Kudos

Hi,

Thanks for your detailed reply. Still I need to know the answer out of those four choices mentioned in my query.

Thanks in advance

somnath_manna
Active Contributor
0 Kudos

I understand from your other posts these are from Sample Certification QB - in that case I would choose

4. first step is distribution via stock transfers

Somnath

Answers (0)