May I know the first step in network planning with SNP from the following:
1. first step is procurement planning
2. first step is production planning
3. first step is deployment
4. first step is distribution via stock transfers
Thanks in advance
First step would be master data setup.
Assuming that is done, then run
1. SNP Low Level Code
2. Run Location by Location Heuristics or Network Heuristic for Finished products (will create STRs / Purchase Reqs)
3. Run PPDS Planning Run or SNP Location Heuristic (depending on material requirement and horizon) to create In-house Production and External Procurement Order
4. Carry out execution steps for completion of Production and Purchase Orders
5. Carry out Deployment and TLB to distribute finished products to demand points of the supply chain (where Location Heuristic was first executed)
Hope this helps.
Somnath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.