on 09-10-2010 4:24 PM
Hello guys,
We have PD/DS implemented just to execute CTP when sales orders are created.
Planned orders are not transfered to R/3 till they are converted to process order in APO system.
Our scenario with APO system should end in this point, but I could notice that some planned orders are been created in R/3 system by the user that we use only in RFC between APO and R/3. These planned orders have action (planned order processing) = APCR, this action doesn't even exist in the customizing table T46AS.
Can you come up with any idea why these planned orders are been created?
R/3 : 4.7
SCM: 5.1
Thanks in advance,
Jackeline
Edited by: Jackeline de Noronha Rodrigues on Sep 10, 2010 8:33 PM
Jackeline,
These orders are created by APO, and then sent to R/3. I don't know your business model, but CTP creates a planned order just about every time you do an ATP. I must assume you are publishing these orders back to R/3.
From SAP help
http://help.sap.com/saphelp_scm70/helpdata/EN/64/7294375960a42be10000009b38f8cf/frameset.htm
"Unlike in the multilevel ATP check, during the CTP process, PP/DS planned orders or purchase requisitions, which are visible and are taken into account in planning, always result immediately. "
There is another similar code as well, APCH. The codes are discussed in the following note.
https://service.sap.com/sap/support/notes/601174
Best Regards,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.