Budget Carry forward and open a new financial year

former_member199650
Participant
0 Kudos

While Carry Forwarding the budget to next financial year,the budget getting carry forward on the project level is the allocated budget instead of available Budget. How to get the available budget only instead of allocated budget in the respective screen? As looking into the allocated budget & supplementing the budget for that project is creating a lot of confusion for that year.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member203108
Active Contributor
0 Kudos

Did you try searching OSS notes?

Former Member
0 Kudos

Hi,

Have you done commitment carryforward prior to budget carryforward?

Also,

run CJEN after carrying forward, and CJBN if using availability control.

Regards,

Harsh.

Edited by: Harsh Saxena on Sep 10, 2010 3:34 PM