on 09-08-2010 2:31 PM
I would like to know if we could do Customer Independent Scheduling agreements in SD. The reason is that we are receiving forecast from a third party tool, which is region specific. I would like to create a scheduling agreement a level above the customer for the entire region. Is this possible in SD. Any help will be greatly appreciated.
Thanks in advance,
Rishi
Hello Rishi
You need to use Flexible Planning / Sales and Operations Planning (SOP) to do this. May be you can use Sales Offices or MRP Areas to denote "Regions' and create plans for a product (material) or group in a custom Infostructure which includes that characteristic. Here is the link to SOP:
http://help.sap.com/saphelp_erp60_sp/helpdata/en/a5/632f3b43a211d189410000e829fbbd/frameset.htm
Hope this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.