on 09-08-2010 7:29 AM
Hello Everyone. I changed the production storage location of one component of a material in ECC and then CIF material and PDS to APO. The planned order created still picks-up the old storage location and the sublocation in the PDS is not updated. What could I have missed? Thanks.
Michelle
Hi,
Check in the BOM item details screen in the Status long text tab page whether Production Sloc is defined with the old sloc.
This will have preference over that is assigned in the material master.
Thanks,
nandha.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I tried simulating the scenario.
My Prodn sloc specified in BOM of the component is Blank.where as my production sloc in MRP2 View of MM of the components
is 4001.
Initially SNP PDS was created with 4001 Sloc for the componets. After this i tried changing the Psloc in BOM of the component to 7001.
Deactivated the Integration model and then activated the IM.
Now 7001 is reflecting in my SNP PDS
Tested with PPDS PDS also. It is working for me.
Thanks,
nandha
Edited by: S.Nandakumar on Sep 9, 2010 7:33 AM
Edited by: S.Nandakumar on Sep 9, 2010 7:36 AM
Hello. That is what i did before i joined this forum. Unfortunately it did not work for me, the subloc field in the pds is not updated when i changed the sloc, even if i maintained the sloc in the bom for the particular component, it has not reflected in the pds in APO. comparing the pds using the comparison transaction yielded no inconsistencies, which is why it is puzzling. any more suggestions? thanks.