on 09-07-2010 8:37 AM
Hi,
We are using network costing for cost planning purpose. We are only using internal activities and work centers for that. I am able to see planned and actual cost in project planning board but I am not able see the same in structural view as per the Project versions. I have checked even RPSCO table to see planned value with respect to WBS but here i am not getting any records for the same.
can somebody tell me what I am missing.
Thank you in advance,
Pramod
Have you created the project version?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
No, I am not doing comparision in PPB, i am seeing only current data in PPB. I am trying to do comparision in CN41 - Structural overview, wherein I can call current as well as version data.
I have stated business case above, problem is we are able to keep track of changing network cost whenever there is proj extension or scope change, so we are using versions.
Pramod
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.