on 09-07-2010 8:17 AM
Hi ,
When i schedule job for a DO in SDOE_BG_JOB_MONITOR always it is getting cancelled.
In job log it is showing the following error: "Control Framework : Fatel Error - GUI cannot be reached".
Error text in ST22 "Exception Contion "CNTL_ERROR" raised"
what could be the reason ?
Server Details:
SAP NW Mobile 7.11 EHP1 Level 002.
Note : Same DO job is working in NWM 7.10 SP09.
Regards,
Kanagaraj .
Hi,
Can you please provide more details like, is it the same DO transported from NWM 7.10 SP09 to 7.11
Or the New DO created in 7.11?
what will job 'SDOE_BG_JOB_MONITOR' do?
Thanks and Regards,
Suma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
After the DOs are transported, is RFC destination created in 7.11 system to connect to Backend?
RFC destination will not be transported as part of DO. After transporting, we have to create a RFC and set it to the Backend Adapter.
The Error clearly says it is unable to connect.
Please check this.
Thanks and Regards,
Suma
Hi Suma,
thanks for your response.
i have created RFC destination in mobile server to communicate with backend.
It is getting the data from BE When i do the manual Delta Download in "SDOE_LOAD" for particular DO.
so error is occuring only when schedule delta download job. I hope now you clear with my problem.
Regards,
Raj