Dear experts
When i execute the T-code S_ALR_87013558 for one proj,I came accross the error"No costs, revenues or finances were selected".Double click it,showing:Message no. OK602.
But when i execute the same proj with S_ALR_87013543,I can get all the cost.
How can I solve it? Waiting for your help,thanks.
Robert, S_ALR_87013558 will give budget, actual, commitment where are as S_ALR_87013543 will give Plan Vs Actual. If you have only planned cost at project, but not budget or commitment or actual cost, then S_ALR_87013558 will not show any values but S_ALR_87013543 will give planned cost. Check if your project has budget or actual or commitment cost. If it is not S_ALR_87013558 wil not work in your case.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Appreciate for your sincerely help.
As to my id,the authority have no problem.
Even the proj had actual cost,S_ALR_87013558 will not work all the same.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Also you can check whether budget related authorizations are provided or not on your id
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.