on 09-04-2010 4:58 PM
Hi,
MY ECC and SRM 7.0 system are in place still my EP server connectivity is still going.
I have set all the conections and configuration in ECC and SRM system, my master data (matl group, material plant company code) everything is available in SRM.
When i created a PR in ECC when i am trying to send the PR to SRM through BBP_EXT_REQTRANSFER it is not getting transfered.
In ECC it is getting held up in SMQ1 with the error "ANORETRY"
"Ext. requirement cannot be created, see application log f"
In ECC i have matained the entries in the table v_t16ex also.
Is there any thing to make changes in the program BBP_EXT_REQTRANSFER where i am using the standard SAP provided.
Sunil
Hi
what is the error in SRM
SLG1 TCODE
MUTHU
Are you getting this error for all purchase request?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In the PDP at the backend system you need to configure two tables T_160PR and T-160EX . once these tables are configured then you need to schedule the report BBP_EXTREQ_TRANSFER. Please check those tables.
Regards
Sameer