Final confirmation issue in project system activities

Former Member
0 Kudos

Dear all,

I have having problem in final confirmation.

I created activities.Planned some scope of work , after completion of the same scope of work I marked Final confirmation as system automatically ask for.But the situation now is that, The scope of work for the same activity is re-planned, It need to be chaged as scope of work increased.

I changed the scope of work, But while confirming from CN25 the same activity number is not getting displayed.

Kindly suggest

Regards

Ashutosh Saraf

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Check Confirmation Parameter txn. OPST. You can change "Default values" & "Selection" as per your business requirement.

Hopefully it will help

Former Member
0 Kudos

Hi,

Kindly elaborate it in detail.On step by step manner.

Former Member
0 Kudos

Hi Ashutosh,

Already Ahmed has explained it step by step. How many more steps do you want? Try what Ahmed has suggested and the revert.

Regards,

Gokul

Former Member
0 Kudos

Dear Gokul,

Ya that worked.

Thanks

Answers (2)

Answers (2)

former_member203108
Active Contributor
0 Kudos

Enter both network and activity number(for which you have set Final confirmation) in the input screen for CN25 and then see whether you can confirm again or not.

virendra_pal
Active Contributor
0 Kudos

Even if you have set the final confirmation indicator (by your default setting - OPST), you should be able to confirm more time in statndard SAP