on 09-04-2010 7:19 AM
Dear all,
I have having problem in final confirmation.
I created activities.Planned some scope of work , after completion of the same scope of work I marked Final confirmation as system automatically ask for.But the situation now is that, The scope of work for the same activity is re-planned, It need to be chaged as scope of work increased.
I changed the scope of work, But while confirming from CN25 the same activity number is not getting displayed.
Kindly suggest
Regards
Ashutosh Saraf
Check Confirmation Parameter txn. OPST. You can change "Default values" & "Selection" as per your business requirement.
Hopefully it will help
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Enter both network and activity number(for which you have set Final confirmation) in the input screen for CN25 and then see whether you can confirm again or not.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Even if you have set the final confirmation indicator (by your default setting - OPST), you should be able to confirm more time in statndard SAP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.