I Planned the Cost (Manual Cost Planning) against Various WBS. Now I want to Post the Actual Cost without any Financial accounting.
Need such data for Reporting Purpose only and to make the decison on the same.
Thanks
Edited by: rmk123 on Sep 3, 2010 2:09 PM
There are many CE Categories used as Secondary. It looks that relevant ot your case is 43. you can chekc CE Categories in KA03 ( give any Cost Element ) press F1 on CE category.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
That can be possible with secondary cost elements as you define in CO.
You can define secondary cost elements assign to Activity Types, with reference to Activity Types, you can post actual cost to WBS elements.
Vemula
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.