Hi experts,

i had run planning run PP_02 run in PPDS and i am able to see dependent requirment for componenets but my question is its not generating planned order for my components. Please let me know if i had missed any config.

Second point is i am planning to run 1. Infinit planning runa nd then finit planning run ( PP-02 and MRP_02).please suggest.

Third is when i run planning run (Product heuristic its giving me an error saying it space constrains.Please suugest me.

Thanks

Raj

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

With the heuristics SAP_MRP_002: Product planning (plan comp. immediately) , components that are defined as being planned automatically and immediately are planned using a simple lot-sizing heuristic.

SAP_PP_001 is for Changing orders manually. Better choice may be to use SAP_PP_002: Planning standard lots. We use this heuristic to create new receipt elements in order to cover product requirements

regards

Datta

Answers (0)