I am trying to create a schedule line agreement (VA31). Cant complete the entire cycle.

I have some questions over here:

1) after going in VA31 what is the ideal option to create a schedule line? DS/LZM.?

2) where do i set the time interval if i want to deliver the goods in intervals?

3) Are there any other parameters which are needed to follow before and after creating the scheduling agreement.

need complete steps for the above.

Thank you

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Colleague,

Please have a look in the note 914607. There a guide/exaplanation concerning your question.

Regards

Ruy castro

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi raju,

thankx for you reply.

but i still have a problem over here.

The options that i get in schedule line are :

COB

DEL

DS

BL

LZM

LZS.

there is no LZ. I am working in SAP V7.10.

Former Member
0 Kudos

as you know ---A schedule agreement contains details of a delivery schedule but a contract just contains quantity and price information and no details of specific delivery dates

Schedule agreements allow you to have 2 different sets of schedule lines in Standard SAP you should have two sets of tabs - of schedule lines. One Forecast & the other JIT. Forecast forwards the schedule lines to planning (seen in MD04)

Go for Schedule agreement doc type: LP here enter the material and the Target qty if u notice net value will not update unless

schedule dates click on Forcase Delice schedule button

In Forecast delivery schedulling tab enter the scedule dates