while creating the installmetn plan i am getting this error "date is outsid

Former Member
0 Kudos

while creating the installmetn plan i am getting this error "date is outside of the permitted range u2013 maintain factory calendar"

is there any oss i need to apply or simple change in below config?

General Settings->maintain calendar-->

Also how to transport the changes from development system to quality and then to produciton?

Edited by: vinod khelani on Sep 2, 2010 6:20 PM

1 REPLY 1

AmlanBanerjee
Active Contributor
0 Kudos

Hi Vinod,

The error you are getting comes only when you are giving a date which is not maintained in the SAP factory calendar.

You need to go to transaction code SCAL and go to the factory calendar in the subobjects section.

Then maintain the year for the specific factory calendar your SAP system is using.

After you have saved the above activity, retrun to the main screen of SCAL and go to calendar in the menu and press transport.

A pop-up will generate requesting for a transport request, and you can create your own and transport the same to quality and Prod environment.

Hope it helps.....

Thanks,

Amlan