on 09-02-2010 10:40 AM
Hi Experts
In my system I have created Statistical Project WBS (with CC posted). I have assigned NW Activities to it and doing all my procurements through Activities.
Everything goes fine (Planning- Budgeting-PR-PO-GR etc.) till settlement.
When I do settlement (CJ88) the system gives error of Budget Exceed (BP604) even when sufficient budget is available on WBS elements.
Can anybody suggest how it can be removed. (Currently I do CJBW then settle and then again do CJBN. But this does not look a good solution to me).
JOHRIP
I agree with Ahmed. There you cannot settle statistical cost of any Object i.e. Order, WBS etc.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sorry, I didnt notice this line
even when sufficient budget is available on WBS elements.
But, I dont think you can settle a statistical WBSE. Can you tell me what you are trying settle and to where?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ahmed/ Nitin
I am doing the following.
I have created Statistical Project WBS (with CC posted). I have assigned NW Activities to it and doing all my procurements through Activities.
When I do settlement (CJ88), for Network Activities, the system gives error of Budget Exceed even when sufficient budget is available on WBS elements.
Currently I do CJBW then settle and then again do CJBN. But this does not look a good solution to me.
JOHRIP
I think here you are setting Netwrok activity to stastical WBS. System should allow this kind of settlement, If budget is there should not get availability control error. Pelase sahre error message no if you are geting the same. System will not allow to settle when you settle from statistical WBS to any where else.
With Regards
Nitin P.
System behaviour is correct. There is nothing wrong.
Network activities will consume the budget of the assigned WBSE. So, for example you have budget of 100 and actual cost of 100 at activity level, now the available budget is 0 for WBS. When you try to settle, 100 will be posted to WBS but now there is 0 budget. So system will not allow you to settle.
Read my very first reply, I have given you the possible solution for this.
HI Ahmed<
The same is happening in my case of settlemnt also. saying budget exceeded.
I am only using WBS elemnts (no activities)
W1: 100 assigned
W2: 50 distributed
W2: 50 distributed.
When i consume 10 at level 2 and then go for settlemnt at W1: showing that budget exceeded.
pls help
regards
Surya
W1: level one WBS: 100 assigned
W2, W2: 2 WBS elemnts at level two: 50 distributed to each from W1
Now i have made a purchase for 50 and posted to w2 (level 2), and at the month end i need to settle 50 at leavl two.
Once i do settelment , the error is budget exceeded.
Correct me if i am wrong: i need to settle 50 to W1 (level1) and then settle W1 (level 1) to AUC.
Hope so now my question is clear.
Edited by: Surya Pampana on Oct 21, 2010 3:30 PM
Hi,
Check your tolerance limit ( It is spossible it is less than 100%) SPRO --> PS --> COSTS --> Budget --> Tolerance limit.
Check this message is due to WBS budget ( and it is not due to Founds management budget) , this is explainned in the message.
If you this all is OK you can execute transaction CJBN in order to repair availability budget...
Regards,
Sara
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you are rolling up the cost by settlement from lower level to higher level WBSE, then budget check will happen. This is std. design of SAP. If you dont want the budget check then either de-activate the Availability control or else you settlement by settlement cost element and exempt those settlement cost element in IMG. So that Budget check will not happend during settlement.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Ahmed
I have no problem with Budget check happening.
The problem is when the system is giving error even when sufficient budget is available.
This is happening only with the case of a Statistical Project.
In my organization, in a parallel system is having exactly the same set-up, just the WBS are not statistical (we are making settlement rule to CC in WBS). There this problem does not happen.
Thanks and Regards.