on 09-02-2010 8:42 AM
Hi,
Management wants to change the PS structure in mid of the project.
Is it possible to transfer data of a network to another network of two different WBS.
For example in WBS.1.01.02 I have a Network 3400001976 and internal activity 34000019760010. & in WBS.1.01.03 I have a Network 3400001977 and internal activity 34000019770010. Now they want to transfer all the details of 3400001977 network to 3400001976 network. Along with all the Material & service consumption & cost details along with all FI transaction happen.
Don't want to do through JV in FI or through settlement rule, b'coz by this no material & service consumption details of the sender network will found in receiver network.
I don't think this is possible or I am not able to find any option in standard SAP R/3, ECC 5.0, is it possible if yes how?
Please help me.
Rgds,
Amlan
Let me share you my experience with it. I think with help of each kind of cost line item get posted in system can be reposted now which transaction to be used it depends up type of cost to be reposted.
KB61: Cost cost where you are hitting FI.
KB65 : For the cost where cost is posted betwen only CO.
I have used above transaction for fe type of cost. It should work. Take help of FI consultant primeraly becaseu in CO, PS can manage.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can also check the manual reposting transactions
KBxxN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Its good to see that you have changed the style of your subject.
Iam not sure about transferring of all data from one activity to another activity. But you can assign the activity of one WBSE to another WBSE. i.e., 34000019770010 can be assigned to WBS.1.01.03 instead of WBS1.01.02 . But, I am not sure how it will work in your case, since you have done many transactions. Just give a try and see it.
If it all you want to transfer the network actiivty to other WBSE, use transaction CN22.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amhed,
Actually I tried this in development server but though the consumption and cost details posted through network and activity to the WBSE in that case if I just change the WBSE No. to the network data remain unchanged for the previous WBSE.
I think this is not possible in standard SAP.
Thanks for your reply.
Rgds,
Amlan
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.