on 08-31-2010 10:01 PM
Hello.
I am executing a forecast on a simple project to try and understand the functionality of the forecast. There is 1 WBS with an Internal Activity with a Material Component assigned. There is no work (ie. work center and hours) on the internal activity. The Material Component has a PReq generated and is in released status. I show commitments on the project of $100 corresponding to the PReq line item for the material cost of $100. There are no actuals and no PO has been created. However, when I execute the CJ9L forecast, the Updated Remaining costs show 0. It is my understanding that the commitments of the material component should factor into the forecast. Am I missing something? Should this not show $100 in the Remaining Costs? Ultimately, we have no spent the $100 yet, so there should be $100 forecast to spend, right?
Thanks.
Let me better explain.
Non-stock material component worth $100. PR created.
- Execute transaction CJ9L
- Commitments column shows $100.
- Updated Remaining Cost shows $0.
In this case, should the commitments and the updated remaining costs be equal?
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks all, but I realize that Non-stock Material Components are supposed to be considered in the forecast. However, it is NOT showing up in the forecast. I know my forecast is working because when I use an internal activity with a rate assigned, I get a value in the forecast. For some reason, the non-stock material components are not showing up. And yes, the Cost Relative indicater is checked.
Any bright ideas? Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Shaun, If the material component is managed in Project Stock, then it will not be considered in Forecast cost calculation. But, if it is a Non-stock item, then the commitment cost will be considered in Forecast cost calculation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please refer note 515716. According to it should read PR for General cost activity the same the case should be other activities.
I never tried in system, but It should read PR just check dates.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.