on 08-30-2010 1:27 PM
Hi ,
If i want to implement SUS for indirect procurement then what is the sceanrio needs to be used.
1.EBP-SUS
2MM-SUS.
If I am using MM-SUS then can de do indirect procurement implementation using this scenario.
Rg
Sameer
Hi
There are couple of options you have, depending on the level of integration you require.
SRM-SUS Scenario --> You can collaborate with Vendor (SUS) for PO, PO Acknowledgement, Confirmation, Invoice. But SRM will work as a standalone deployment with only FI updates happening in ECC
MM-SUS Scenario --> You can collaborate with vendor for PO, PO Acknowledgement, Confirmation, Invoices etc. Document exchange happens between MM and SUS for all documents in this case. Classic as well as Extended Classic(With some modifications) can work in this case
Regards
Virendre Singh