Planned hours in workforce planning

Former Member
0 Kudos

Hi,

Planned hours in workfforce planning transaction CMP3 for network activity is disappearing after 4 weeks. Anybody has idea how this is happening? does any thing missing in profile?

Thanks,

Sudhir

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Now do the following and let us know the status.

Define the CMPC-Work force planning Profile as following:

General View:

Date Type: Cawlendar day

Period Unit: Week

In Period Split View:

No: 3

Period: Week

No. of Periods:4

Now you can try the your scenario by specifying the period as

start date:01.08.2010

Finish Date:31.12.2010

Vemula

Former Member
0 Kudos

Thanks

Sudhir

Answers (2)

Answers (2)

Former Member
0 Kudos

Check your settings of planning period in CMPC i.e. WFP profile

Former Member
0 Kudos

Hi,

Workforce planning profile is ok . Period unit is - Week and no period split

Thanks,

Sudhir

Former Member
0 Kudos

Hi,

Refer the following F1 help given by SAP, for Period split.

Number of periods in a period unit

Specifies the number of period in the period split that have the corresponding period unit.

Note

The system can display up to 50 periods.

Example

You have entered a planning period for workforce planning starting 3 months before the current date and ending 12 months after.

For this planning period you specify the following period split:

Period no. Period unit Number of periods

1 Week 11

2 Day 20

3 Week 4

4 Month 3

This means you display the past period at the start of the planning period in weeks. For the immediate future you select a very detailled display in days. For the more distant future you need less detail and therefore choose progressively longer periods.

If the period split does not cover the whole planning period, only those periods are displayed that have been defined. The system, however, does read the data for the whole planning period, so that you can display the missing periods by changing the period split in the transaction.

vemula

former_member203108
Active Contributor
0 Kudos

Vemula, thanks for your contribution, but please advice user to read F1 help document and dont copy & paste the entire help content in the thread.

Former Member
0 Kudos

Hi,

Can you check following points in the Work force planning profile Date type, Period unit (Ingeneral Tab)

and In period split Tab Period unit and No. of Periods.

You can define the work force planning profile as below:

Date type: calander days

Start date: 01.08.2010 (keep on chenge as per the requirement)

Finish date:31.08.2010 (keep on chenge as per the requirement)

Factory Calendar ID: enter the value(F4)

Fiscal Year Variant:Enter the value(F4)

Period unit: day

In Period Split Tab:

No : 2

Period unit : Day

No.of periods: 20

Vemula