Hi Expert,
We have to required change Payment term of Customer (ZTERM) in scheduled Agreement,
we have gone through Mass, but presently no object type available to change in scheduled Agreement, So can we add the new object in Mass? & How? Please help.
Regards
BK GAIKWAD
Hi,
As already mentioned, it is not available for Schd Aggmts as of now and you cannot do anything on S.Agreemt using MASS. You have to either use the respective BAPI or CATT or LSMW.
Check the bapi BAPI_CUSTSCHEDULAGREE_CONFDELV if it suits ur purpose.
May be the bapi MASS_CHANGE_SCHED_AGREEMENT can help you better.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Presently no standard object type avaialble for Sch. agr.(Sales)
Go for BDC for updation of your field (try with LSMW also)
Thanks
Chidambaram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.