I have a small issue. We are using Assembley Processing in SAP where the Sales Order creates a Project / WBS / NEtwork Order automatically.
If I look on the network order there is a clear link between the order and Sales Order and it also has the requested delievery date in there which is correct however the network order finish date is completley wrong.
The scheduling settings are backwards and lets say the delievery date is 01.04.2011 and and it takes 1 month to finish the project therefore it should start on the 01.03.2011 yet the finish date in the Network Order is way in the future. E.g. it is starting on the 01.05.2011 and finishing on the 01.06.2011 which is wrong.
It seems like it isn't even considering or looking at the customer delievery date.
Regards
Adeel
Schedule your network manually (not by giving date in sales order) by giving the finish date, and see whether it properly derives the start date or not.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear, I am aware of this
And there is no point doing it manually or there is no point using Assembly Processing.
But why i asked you to schedule the network manually, is to find where the problem really lies. If you are able to schedule the network manually and derive the result as desired, then you can conclude that nothing wrong in network scheduling and its parameter and the problem would be the flow of date from SO to network.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.