Component Availability check during MRP Heuristics

Former Member
0 Kudos

Hi Experts,

I am running MRP heurstics to create plannerdorders, during this time i would like to check component availability (planned order/production orders, stock etc).

I don't want to create planned order if component is not available. I don't want to create new PR/Planned order for component.

Component is produced in the same plant.

Regards,

Vipul

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

It is not possible in standard functionality.

Former Member
0 Kudos

Hi Vipul,

Have you tried in PPDS, single-level MRP heuristic SAP_MRP_001 ?

This will run only at single level and not run heuristics for the components.

Regards

Data