on 08-27-2010 4:46 PM
We are currently experiencing a problem with SNP EE planned order publishing to ECC. Specifically around the Opening Date on the planned order in ECC once published.
The opening date is being calculating in calendar days and is not utilizing the production calendar associated with the location. The calendar in the time stream ID is setup with M-F we working and Sat and Sun as non working.
When reviewing the F1- Help on the opening period field on the PP/DS tab in the product master in APO, it indicates that it utilizes the production calendar.
From the F1-Help.
"The production calendar for the location is a decisive factor in determining the opening date"
Anyone know what we might be missing?
Hi Bruce,
Please check one more. In the SNP planning book, load data and right click on the week and check the period information, start and end date of the week should be same as your factory calendar. If it is correct, then not issue in the APO side. Check whether the R/3 Factory calender week assignment is correct.
Regards,
Saravanan V
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bruce,
I assume, production calander is the Factory calander. In the time stream id of the plant "Header data" tab please check correct plant calendar assigned against Working Time Calender.
Thanks,
Saravanan V
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.