Track changes in Copy Planning (CJ9F)

Former Member
0 Kudos

Hi,

I am using CJ9F for copying values from one version (Version 0) of the project to another (lets say version 200). Now, lets say after 10 days, some one re-runs this which will over write the values in Version 200. Is there a method (or report) where in we can see the changes happened to Version 200. For instance, last changed on, last changed by, values before and after the last change.

Note: We need it to overwrite as some time there would be a genuine reason for re-runnning this and copying the values from one version to another.

Regards

Sreekanth

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sreekanth,

First option is Lock your version as soon as it is created

If you don't want to lock your version, then I think you need to develop a custom report.

vemula