on 08-27-2010 4:30 PM
Hi,
I am using CJ9F for copying values from one version (Version 0) of the project to another (lets say version 200). Now, lets say after 10 days, some one re-runs this which will over write the values in Version 200. Is there a method (or report) where in we can see the changes happened to Version 200. For instance, last changed on, last changed by, values before and after the last change.
Note: We need it to overwrite as some time there would be a genuine reason for re-runnning this and copying the values from one version to another.
Regards
Sreekanth
Hi Sreekanth,
First option is Lock your version as soon as it is created
If you don't want to lock your version, then I think you need to develop a custom report.
vemula
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.