on 08-27-2010 10:20 AM
Stock of old material 200 cases as on today
Forecast of new material after 1 month say on 25 th SEP
Then substution receipt is created with delivery date of 25 th SEPT
As stock of old material is availble immediately , substution receipt
should be created immediately i.e. with today's delivery date
What needs to be done
Please advise
Hi,
Please maintain interchangeability masterdata to acheive this functionality.
You can define Product substitution as well as 'use up strategy' (use of old material stock) here.
Transaction is (/INCMD/UI).
If you would like to trigger this from GATP create ATP rules and attach your interchangeability group to it.
For SNP you need to activate interchangeability in 'SNP global settings.
Best Regards,
Deepthi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
6 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.