get earliest finish date for a task of cProject

Former Member
0 Kudos

i found this method CL_DPR_TASK GET_SCHEDULE_ATTRIBUTES to retrieve earliest finish date.

but i don't know how to assign the parameter IR_SCHEDULE_OBJECT to this method.

could you help me with this?

if i don't use this class, is there any other way to fetch the earliest finish date for a task of project?

Edited by: Duan ZZ on Aug 26, 2010 5:11 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Use BAPI_BUS2175_GET_DETAIL to fetch the earliest / lastest dates.

Regards

Sejo

Former Member
0 Kudos

the FM did not retrieve me anything when i pass my task guid to it.

have you ever encounter this problem before?

Former Member
0 Kudos

Hi,

Have you passed the correct GUID?

I have tested it in my system. It returns the required data.

Regards

Sejo

Former Member
0 Kudos

thanks sir, found I passed a wrong ID.