on 08-25-2010 2:05 PM
Hello Experts,
Is it possible to create JIT release lines in APO, if yes how ?
Would it be possible to have fix SNP or PPDS production horizon for JIT lines ?
Please pour in your thoughts
Thank you.
Rahul Chitte
Hi Rahul,
As per Std SAP process, In the SAP APO system, scheduling agreement
(SA) releases take the form of operative and forecast/planning delivery schedules.
You can use this function to create operative delivery schedules or forecast/planning
delivery schedules against APO scheduling agreements.
SA releases against OLTP scheduling agreements (that is, forecast and JIT delivery
schedules) are created in the OLTP system.
JIT scheduling agreement exists in SAP APO. As of SAP R/3 Enterprise Core 4.70 it
is possible to transfer EA scheduling agreements via the CIF. For JIT scheduling
agreements you must have a SAP R/3 system with Release DIMP 4.71.
JIT scheduling agreements with processing by an external agent is not possible.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.