CN01 assign Material Component to internal activity

mariano_sabiche
Active Participant
0 Kudos

Hello gurus;

In transaction CN01 / CN02 can I assign only one Material Component to internal activity without Bill of Material (BOM)?

It is possible? How can i do?

Best regards,

Mariano

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

You need to use Material BOM for adding components in CN01

mariano_sabiche
Active Participant
0 Kudos

Virendra;

Thanks for your response.

I saw the SAP Help portal in [http://help.sap.com/saphelp_46c/helpdata/es/4c/227a7746e611d189470000e829fbbd/frameset.htm]

and I must use a Bill of Material to assign material component. There is no other choice

This is the point where I disagree with SAP, cause the client says that they use Operational Networks, cause it's more simple to assign components to activities.

Best regards.

Mariano