is it possible to change the start of cycle date in strategy maintenance plan (MPLA- STADT).

The start of cycle was entered incorrectly into the strategy maintenance plan (IP42)

Maint. plan was already started

...and called: Service orders are already created

The existing maint. plan should be used with a new cycle start date.

By using u201Crestartu201D in IP10, a new start of cycle date is entered and the orders are called correctly.

But the cycle start date is not updated in the data base: MPLA- STADT

Why?

Regards,

Philipp

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

You can check in MHIS for the same plan where for each call where you can find the planned date and start of cycle ..

regrds

pushpa

Former Member
0 Kudos

Dear Pushpa,

thanks a lot for your answer. I already thought about that, too.

But the problem with this solution is, that in all lists (e.g. IP16 - Display Maint. Plans List), the "old" start of cycle date is shown.

This will lead to confusion.

Do you have any idea how to really change the field?

Regards,

Philipp

Former Member
0 Kudos

Hi ,

Gud question ..

You need develop a ZProgramme by copying programme of IP15 or IP16 and make changes to add additional field .. also check if your in ECC6.0 plz check if Enhacement Spot ES_MPLAN_CHECKS ,MPLAN_BADI_EXTENSION in SE18 ..are helpful

regrds

pushpa

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear all,

I opened a OSS message. SAP replied that this is not covered by SAP standard. so system works as designed.

SAP:

The described behaviour is the SAP/R3 standard and works as designed.

IP16 only shows this field if it's updated in MPLA-STADT.

The 'Cycle start' resulting of scheduling (IP10) is kept in the table

MHIS (field STADT).

Transaction IP16 takes data from MPLA and does not read the entries

in MHIS. The only value that can therefore be shown as 'cycle start'

is the original value as recorded in MPLA.

Well, this explains why system behaves like it does.

But in my eyes this is not the correct system behavior.

If a maint. plan is restarted, future calls will be calculated based on

the new cycle date - what is ok.

But IP16 indicates the old cycle date!

In my eyes this is not correct because the list will show an incorrect

cycle date.

I was told to take a look at note 11:

-

-


Sehr geehrte Kundin, sehr geehrter Kunde,

die von Ihnen benötigte Funktionalität ist leider nicht im SAP-Standardsystem enthalten.

Wenn Sie mit SAP an zukünftiger Produktfunktionalität arbeiten möchten, empfehlen wir Ihnen, dies entweder über die Mitarbeit in einer SAP Anwendergruppe oder über die Mitarbeit in einer der SAP Communities of Innovation zu tun. Eine Liste aller SAP Anwendergruppen finden Sie unter http://www.sapusergroups.org.

Eine Beschreibung der SAP Communities of Innovation können Sie unter http://www.sap.com/ecosystem/communities/index.epx einsehen.

Alternativ können Sie spezielle, von Ihnen gewünschte Funktionalität von SAP Custom Development entwickeln lassen (http://www.sap.com/services/bysubject/customdev).

Weiterführende Informationen finden Sie unter http://service.sap.com/rollin.

Mit freundlichen Grüßen

Ihr SAP Active Global Support

-

-


How can I trigger such an improvement?

Regards,