settlement rule settings

Former Member
0 Kudos

hi

i have a doubt that how will i configure for getting internal order number and costcentre defaulty in settlement rule. please help me

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

You cannot get both ..

1. First in config under PM -->Maintenance and service processing -->Basic settings -->General Order Settings -->Maintain Settlement Profiles .Here under valid recievers for order and cost center you can maintain settlement as optional and in dfault object type under Default Values sub-screen you can maintain CTR or ORD .

2. After doing to above change you need to maintain cost center or internal order no in account assignment data in technical object in eqpt or F.loc master record.Thus when u create Maintenance order on this technical object then settlement rule gets defaulted with receiver mentioned in technical object master record.

3. If you want to have some default settlement rule on your own then do the config point 1 and then use user exit IWO10027 User exit: Generate user-defined settlement rule which you can use to generate settlement rule of your requirement based on order type or other condition..

regrds

pushpa

Former Member
0 Kudos

i do this configuration but i get only the cost centre but i want the internal number also defaulty.

Former Member
0 Kudos

Hi ,

As said above in the settlement profile maintain valid receivers as order and cost center and do not maintain default object type and now u can use user exit IWO10027 User exit: Generate user-defined settlement rule which you can use to generate settlement rule of your requirement based on order type or other condition..

Please chek the above ..

regrds

pushpa

Former Member
0 Kudos

hi pushpa

thank u for ur replay but i dont know how to run the user exit. so give me some need ful.

Answers (0)