on 08-24-2010 12:12 PM
Hi all,
While creating new WBS element in exiting project, system giving error " no changes in WBS possible as budget is activated"
Due to this we need to deactive the AVAC to add WBS element in exiting project. Again run CJBN t.code to activate the AVAC.
I also checked user status. There is no user status which can restrict to create WBS.
Pl guide. What are the possibilites?
Hi,
Can you provide me the status information of Proj Def and at what level you are trying to add new WBSE, status of WBSE to which new WBSE to be added.
and also as Rifaee says, check your project Validation profile for each object.
Best Regards,
Vemula
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think this is due to some validation check. Check your error message and also check is there any validation set for the project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srikanth,
Once you can check with System status (CRTD) Business transaction tr.Code: BS22
and user status (ZAPP) Business Transactions ; tr.Code: OK02.
As you are saying that there is no validation for the any of the object (Project Def. and WBS Element).
It might be problem with Status profile where you have restricted the change option.
Pl. carefully check above mentioned points with your project WBSE status.
Vemula
Hi,
Please check the User Status and Can you please arrange to provide message class and message number ?
If possible long text also much helpful.
Swapnil Kharul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check again. There has to be some User Status that is prohibiting from making any changes to the project structure once budget is activated.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
We used same status profile to project def and WBS.
In status profile we defined status
1) ZWBS. It is initial status. In this status, following business tranction are controlled
Partially confirm WBS forbidden
Partially release project forbidden
Release forbidden
Write budget line items allowed
Write plan line items allowed
and
2)ZAPR. In this status, following business tranction are controlled
released allowed.
I am not getting why the system is not allowing to create new wbs element in exiting project.
Pl suggest the possibilities.
______________________________
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.