on 08-23-2010 1:59 PM
we have a situation here.
when i see in co09 it looks like following. I am not able to understand why sales order of 70 is not getting confirmed though ample reciept element is available (pch ord)? and why sales order of 350 on 25th aug is getting partially confirmed?
Date time category document receipt/req conf q cuml atp q atp q
08/23/2010 08:12:14 Stock Distribution Center 70 0 280- 0
08/20/2010 09:58:00 Deliv. 70- 70 280-
08/20/2010 23:59:59 Deliv. 70- 70 280-
08/20/2010 23:59:59 Deliv. 140- 140 280-
08/20/2010 23:59:59 Deliv. 70- 70 280-
08/24/2010 12:00:00 PchOrd 1,540 0 0 0
08/25/2010 00:00:00 SalesOrder 70- 0 0
08/25/2010 07:00:18 SalesOrder 350- 0 0
08/25/2010 07:00:18 SalesOrder 0 280 0
moreover why last column (atp quantity) is showing 0 quantity when pchOrd OF 1540 is available? on later dates last column has recipt quantity visible. example-
09/07/2010 00:00:00 PchOrd 350 0 350 350
09/07/2010 00:00:00 PchOrd 1,470 0 1,400 1,050
am i reading it correctly? is there any link which says how to read these results?
Hi ,
There can be two reasons for non confirmation/ partial confirmation.
Do you have product allocation active ?
Has Customer exceeded credit check?
Thanks,
Pavan Verma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Both,
Thanks for you reply.
This product is not there in allocation. I checked change history of sales order. it says confirmed quantity was changed on a particular day by user "ALEREMOTE". There is no such user. Does this mean it was changed during backorder processing run??
Even if was changed by BOP, I am not able to understand why BOP will do partial confirmation even if complete material is available?
No it does not give full confirmation!! it goes to proposal screen ( we have maintained RBA) and shows different location from where it can get rest of the unfulfilled sales order.
This is something i am not able to fathom, it should propose another location only if there is no stock available at requested location right? i tried looking at mmbe to find if stocks are getting consumed somewhere else, but it seems fine to me. am i missing anything here?
Hi,
check your BOP settings. It is possible that you run the BOP with check confirmation or that the "rules again" flag is not
activated. This means that BOP with just recheck the subitem without executing the rules again for this requirement.
Activate the rules again flag and recheck with a BOP simulation.
Yes, ATP will change the plant just if not all of the requirement could be confirmed in the first checked plant.
Hope this helps.
best regards,
Michael
Madhu,
It is not config, it is part of runtime. /SAPAPO/BOP > Parameters check tab
Check prerequisite settings
http://help.sap.com/saphelp_scm70/helpdata/EN/c6/958139a17cd02ae10000000a11402f/frameset.htm
Best Regards,
DB49
Edited by: Dogboy49 on Mar 29, 2011 10:37 AM
Dear Illford,
Unfortunately it is hard to say why you did not get any confirmation.
Please recheck your customizing in scope of check for receipt elements and if past receipts will be considered or not why gatp check.
Regards,
Tibor
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.