Hi,
We want to transfer a Finished goods BOM with Phantom item to APO as PPM. Can anyone suggest the steps required for the same. We already tried to transfer, instead of Components, Phantom item is getting transfered and getting assigned to different operation in PPM.
Thanks in advance.
Regards,
SP
Hi,
Please refer to OSS note 448085 PPM Transfer Tips and Tricks
It clarifies that during CIF transfer Components that have the phantom item indicator are not transferred.