Budget exceeds error in INR

Former Member
0 Kudos

Hi ,

My controlling area currency is INR.

I budgeted a project in USD while creating a PO in USD I am getting budget exceed error shown in INR the error must be in USD.

I am unable to change project currency in WBS as there are multiple company codes for one controlling area.

Pl sugest.

Rgds

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Shrikrishna,

Now you can do the following changes in the budget profile and test whether it is working?

Under Availability Control Parameters:

Availability check Control as "1" and also check Object Currency

Budget Currency Parameters:

Check Object Currency.

Pl. update the result.

Best Regards,

Vemula

Former Member
0 Kudos

Hi Srikrishna,

In Tr.Code: OKKP -Activate Project Management in Controlling Area,

Choose your CO Area, and open the screen of "Activate Components/Control Indicators" then check for

whether "All Currencies" indicator is checked or not.

Best Regards,

Vemula

Former Member
0 Kudos

Gokul ,

I am using transaction currency in budget profile.

Vemula ,

The suggested indiacators are ticked.

Former Member
0 Kudos

Hi,

What is the currency you are using in the budget profile? Check that.

Regards,