MM-SRV-SUS: Setting for Service Procurement SRM7.0 ECC 6.0 Ehp4

Former Member
0 Kudos

Hello,

I have to implemente the service procurement scenario between MM and SUS.

Can you explain me what are the main settings that I have to make in order to implement the service procurement scenario ?

It'is very irgent.

Please help me.

Good work,

Michele

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Follow all the steps given in SRM 4.0 config gidue(plan driven procurement) to set up, make sure all the PI configuration is done.

Following use PI path for replciating the documents from ECC to SUS and vice versa: PO and Service confiramtion rest of them are still on IDOC.

To enable replication of PO and service confiramtion follwoing workflow need to enabled in SWETYPV:

BO BOR object type BUS2012(PO) CHANGED WS3800008

BO BOR object type BUS2012(PO) CREATED WS3800008

Limitation is only free limit PO are replicated to SUS, contract limit and Overall limit is not supported.

with regards

Manjunath