on 08-18-2010 3:37 PM
Hi,
Can we use ChaRM for performing regular transports in the landscape.
If so, what should be the project type?
Regards
KVR
Hi ,
Basically there are a few types, mainly on maintenance project, implementation and template project.
In this case, for more ChaRM information please visit our expert blog such as
First steps to work with Change Request Management scenario
/people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-management-scenario
Change Request Management scenario: Usual questions
https://weblogs.sdn.sap.com/cs/junior/view/wlg/15116
Change Request Management scenario: Working examples
/people/dolores.correa/blog/2009/07/23/change-request-management-scenario-working-examples
Hope this helps.
Cheers,
SH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Based upon the requirement you can create a
Implementation project
or
maintenance project
both support CHARMS
it is all upto requirement of your project
hope it helps
Regards
Prakhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Based on what I read, Maintenance project cycle ends every 3 months and all the changes will go to production at the end of cycle and of course there is emergency transport as well.
Our project is in support stage. we move transports to production once in every week, and we also do some emergency transports each day. I am just wondering how I should use ChaRM here.
Regards
KVR
User | Count |
---|---|
82 | |
10 | |
10 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.