on 08-18-2010 8:13 AM
Dear Gurus,
Please explain Work center routing and how it functions?
Regards,
PMAddi
Thanks gurus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Work centre is a place in Shop Floor where a sequence of operation or a single operation is happening and the activity are measured in terms of cost ( machine , labour ,set up) are estimatted here with help of certain formula assinged to Work centre .
It control the operation based on Capaicty , schedueling , Cost, Goods Reciepet through a Control key .
Work centre can be assined to any operation for any routing .It is not material specific rather plant specific.
Where as routing is a sequnece of operation .Routing can have one single work centre to each operation or different work centyre assinged to various operation in a routing .From PP point of view , routing are always created for Finshed Good , Sub -Assmbly which will be producted through a sequence of operation .
However , a routing can be created for Network , Plant Maintainenec purpose , production purpose .In SAP ,they are indicated as usage of routing .For Production it will be 1.
Work Centre -One Time PP-Master Data -
1.CR01-Create Work Centre
2.CR02-Change Work Centre Data
3.CR03-Display Work Centre Data.
Routing Creation :
1.CA01-Create Routing
2.CA02-Change Routing
3.CA03-Display Routing .
Hope this will give you an idea .There are plenty of threads available in forum .
Regards
JH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Addi,
Routing - Sequence of operation to get the uotput
There are two type of Routing - 1. Routing (CA01) 2. Rate Routing (CA21)
1.Routing (CA01 ) - is used in descret manufacturing , while creating the routing you put the planned activities for the operation
2.Rate Routing (CA21)- in rate Routing operation ,Quantity and duration is fixed it is used for the Repetative manufacturing
Tables for Routing are - MAPL ,PLPO, PLKO
WorkCenter- Where actual operation of routing are performed.
TCode- CR01
In work center you assign standard value key , These values are used as a activity for product costing Purpose for that you need to select formula in costing Tab.
You can define the capacity as well as Shifts grouping in Capacity Header.
Table - CRHD
Please revert back if any specific information is needed
Regards
Girish
Edited by: girish khobare on Aug 18, 2010 9:40 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Kindly read the help.sap.com for the below topic.
It is self explanatory and then come with the specific questions.
Workcentre: These are the Places where the operation isperformed.
Routing ; This is the sequence in which opeation are performed.
Reg
dsk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.