Classic Scenario:

1. Create a Limit SC with Between Dates (date Range) with a sUpplier

2. PO is created in BE only with a delivery date.

I would like to get the date range in the header of the PO. Thoughts!

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

What is product type in SRM. For 01, the delivery date is not picked up in range. For 02 it will be picked up in date range and make sure that data transfer is happening with proper date category to backend.

Check BBP_PD details for checking how date and product type sare picked up in SRM SC or PO

Regards

Virender Singh

Former Member
0 Kudos

Thanks for your response.

As per SAP the xml interface does not have the fields structure to carry the date range in case of a classic PO. Meaning as standard SRM7, Classic scenario, limit PO will not have FROM and TO dates for now.

SAP is helping me with a note. Will let you know once i get that. Thanks

Former Member
0 Kudos

Here you go.

Use below SAP note for getting from and TO dates populated in ECC PO from SRM SC.

This note will be released as part of SRM7 SP09.

SRM 7

Classic Scenario

XI msg from SRM to ECC

SAP note 1503941 and 1505317 in ECC and SRM respectively.

Message Closed. Thanks

Edited by: Netaji Gummadi on Sep 13, 2010 3:29 PM

former_member183819
Active Contributor
0 Kudos

THANKS

From and to dates not transferred to backend PO in case of limit shopping carts.The validity period in the backend is blank because of this

SP 10

the note might be created after you have reported.

YES THIS NOTE they kept it in SRM-EBP-ESA componenet .......rather than limit component

Former Member
0 Kudos

Issue resolved