APO planned orders doesnu2019t have scheduling view in ECC

Former Member
0 Kudos

Dear Experts,

I am new to Apo PPDS and We are facing typical problem in SAP ECC u2013APO integration.

The APO PP/DS orders are CIFed to ECC but it is not populating the detail scheduling tab of planned orders of SAP.

Please let me know the reason.

Regards

Sandeep

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Please check whether scheduling parameters for planned orders (OPU5) is defined for the order type , plant and scheduling parameters.

Thanks,

nandha

Former Member
0 Kudos

Hi Sandeep,

There is a configuration setting R/3 for planned orders so that the scheduling tab can be populated by default.

Please check the config and your scheduling tab will get populated.

Regards,

Asheesh

Former Member
0 Kudos

Hi Sandeep,

Carry out /sapapo/ccr for planned orders and check whether any

errors are getting captured.

Also check the publication definition settings in APO customisation.

Regards

R. Senthil Mareeswaran.