Postprocessing - background processing - Still running!!!

Former Member
0 Kudos

Hi All

I think I am having a small problem with this task 'Postprocessing - background processing' during the Postprocessing Phase. Basically on previous runs, this task has finished quite quickly however during this next run it is taking hours. I have restarted this phase and it does not seem to finish.

I have checked SM66 to see if anything is running and there is nothing there. All of the other processes have finished successfully, just not sure about this one.

Has anyone had this issue before or can you give me an insight to what it is doing?

Thanks in advance

Phil

Accepted Solutions (1)

Accepted Solutions (1)

former_member182566
Active Contributor
0 Kudos

Hi Phil,

The task 'Postprocessing - background processing' is actually made of several tasks (switch to Extended View to be able to expand them). Which of the sub-tasks is running?

Have you checked SM66 in all systems (tdms, sender, receiver) ?

Rui

Former Member
0 Kudos

The process that are involved in the task are:

Reset Internal Header Tables After the Transfer - Complete

Postprocessing - background processing - This one has not completed

Transfer of Number Range Intervals - Complete

Reset Number Range and Table Buffers in Receiver System - Complete

Delete Generated Views - Complete

Adjust User Addresses - Complete

Update SAPOffice - Complete

Execute Initialization for POS Handling - Complete

Change Logical System Names - Complete

Unlock Users in Receiver System - Complete

Refresh Data Selection Cluster of Current Transfer - Complete

I am just curious to know what it does, also these is nothing happening in any of the systems.

Thanks

Phil

Former Member
0 Kudos

Just try to restart the following activity only -

Postprocessing - background processing - This one has not completed

former_member182566
Active Contributor
0 Kudos

>

> The process that are involved in the task are:

>

> Reset Internal Header Tables After the Transfer - Complete

> Postprocessing - background processing - This one has not completed

> Transfer of Number Range Intervals - Complete

> Reset Number Range and Table Buffers in Receiver System - Complete

> Delete Generated Views - Complete

> Adjust User Addresses - Complete

> Update SAPOffice - Complete

> Execute Initialization for POS Handling - Complete

> Change Logical System Names - Complete

> Unlock Users in Receiver System - Complete

> Refresh Data Selection Cluster of Current Transfer - Complete

> Phil

"Postprocessing - background processing" is not actually a task, it is there only to group the sub-tasks (from "Transfer of Number Range Intervals" to "Change Logical System Names"). When you execute it, it will run all the sub-tasks (in the Standard View this complexity is hidden, so you don't even see there are sub-tasks).

If the sub-tasks are all Complete then there is nothing left to do. It is normal that there is no State icon for that grouping task, or that Progress is 0. If you execute it again you are running all the sub-tasks once again (you probably received a pop-up to confirm that's what you wanted). In that case, the column "Exec No" in the sub-tasks probably shows that some were executed more than once (some are repeatable and some are not).

Hope this helps,

Rui Dantas

Former Member
0 Kudos

Thank you all for your answers.

Rui, I agree with your point and have now completed the process, the end users see no issue so everyone is happy.

Thanks

Phil

Former Member
0 Kudos

HI phil

This is Mayu I had aproblem in User attribute modification.Unable assign roles to user in EP 7.0.I think u might be face the same issue and need ur solution.

How to solve this give me ur mail id so tht I can send u the eror log..

Immediate help is appreciated n awarded

Thanks \

Mayu

Answers (1)

Answers (1)

Former Member
0 Kudos

Goto the extended view and see against which step you have the truck icon.

If in SM66 no entry exists,then check the job logs to see if any job failed in either Control/Receiver system

If all the steps within "Postprocessing - background processing" have a yellow or green,you are good to go...It might be an issue with the status maintainence of that step.