Hello,

I try to plan on Network Activities with ECP, however, although I configured all necessary customizing yet I cannot see any NWA on the ECP GUI.

This problem was allready discussed and solved at this forum but non of the suggestions help me to solve it.

The required configuration steps I allready made:

1. Activate planning for network activities with ECP

2. Define CO version for ECP

3. Activate multiple CO version

4. Define Alternative CO version

The network contained a costing variant for planning

Thanks and Best Regards,

Nir

Edited by: Nir Horvitz on Aug 17, 2010 9:25 AM

Edited by: Nir Horvitz on Aug 17, 2010 9:29 AM

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Did u activate the ECP for activities??...check below configuration.

Planned Cost ->Easy Cost Planning and Execution Services->Easy Cost Planning->Activate Planning for Network Activities with Easy Cost Plan

Venkat

former_member203108
Active Contributor
0 Kudos

Venkat, you should read Nir's thread completely. He has listed out what he has done so far to achieve.

Former Member
0 Kudos

From where did you get the ECP can be used for Networks activities?

former_member203108
Active Contributor
0 Kudos

Venkat, read EHP3 documents for Project System. ECP for network is available from EHP3.

former_member203108
Active Contributor
0 Kudos

Make note of your control key of the activity, then goto OPSU, open your control key settings, and check whether "Cost" box is ticked or not. If it is not ticked, you will not see those activities in ECP screen.

Former Member
0 Kudos

Hi Ahmed,

Thanks for your reply.

"Cost" box is active at the activity's control key.

I will be glad for more ideas for solving this issue.

Best Regards,

Nir

Former Member
0 Kudos

Hi all,

I refresh this thread hoping to get more information.

Thanks,

Best Regards,

Nir

former_member203108
Active Contributor
0 Kudos

Nir, I am not sure, but try this, goto OPSC, tick the check box "Planning" for your network type and then create a new project with the activities(using that network type) and then execute ECP and see.

Former Member
0 Kudos

Thank you Ahmed for your efforts, however, I have tyried your suggestion but NWA still not appears.

I have openned an OSS to SAP support about this issue and if I get a solution I will update this thread.

Sure I will be glad to an additional ideas.

Best Regards,

Nir

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Yes I do. I get The WBS's for costing on the GUI screen but the NWA's are not appears.

Former Member
0 Kudos

Hello colleagues,

I finnally got an answer from SAP support about this issue.

The answer is very simple and was sliped away from my mind...

Activity Account assignment have to be activated. in the case of header assignment ECP planning method cannot be implemented.

Thanks,

Best Regards,

This thread is closed.