on 08-17-2010 8:23 AM
Hello,
I try to plan on Network Activities with ECP, however, although I configured all necessary customizing yet I cannot see any NWA on the ECP GUI.
This problem was allready discussed and solved at this forum but non of the suggestions help me to solve it.
The required configuration steps I allready made:
1. Activate planning for network activities with ECP
2. Define CO version for ECP
3. Activate multiple CO version
4. Define Alternative CO version
The network contained a costing variant for planning
Thanks and Best Regards,
Nir
Edited by: Nir Horvitz on Aug 17, 2010 9:25 AM
Edited by: Nir Horvitz on Aug 17, 2010 9:29 AM
Did u activate the ECP for activities??...check below configuration.
Planned Cost ->Easy Cost Planning and Execution Services->Easy Cost Planning->Activate Planning for Network Activities with Easy Cost Plan
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
From where did you get the ECP can be used for Networks activities?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Make note of your control key of the activity, then goto OPSU, open your control key settings, and check whether "Cost" box is ticked or not. If it is not ticked, you will not see those activities in ECP screen.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello colleagues,
I finnally got an answer from SAP support about this issue.
The answer is very simple and was sliped away from my mind...
Activity Account assignment have to be activated. in the case of header assignment ECP planning method cannot be implemented.
Thanks,
Best Regards,
This thread is closed.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.