Hi All,
I have a sales order with a requested delivery date of 08/31/2010 -
Schedule line confirmed with a delivery date of 08/31/2010 and Goods Issue date,Material availability date and other dates of
08/25/2010.
when i create a delivery system creates with a planned gi date of 08/27/2010.I dont have any pick / pack time
Please help me understand how system is calculating planned gi date in the delivery.
Thanks
Meghna
It is depend up on material availability date.
Scheduling date are prposed by the system by backward scheduling(in general)- if stock is not found as per requested date, then forward scheduling will be done and confirms new dates.
In your case- system proposes
In your case system considering transit time and transportation planning time- (from route)- then calculated loading time and GI time and proposed GI date
For Transportation and delivery scheduling- refer
http://help.sap.com/saphelp_47x200/helpdata/en/dd/5607e7545a11d1a7020000e829fd11/frameset.htm
Thanks
Chidambaram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Meghna,
The system automatically calculates the goods issue date by taking into account the following factors:
The requested delivery date
The pick/pack time
The loading time
The transit time
In your case, I think system is considering the Intransit time. The intransit time depends on the route.
Please check your Route settings.
Hope this helps
Thanks
Murtuza
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.