Dear PS gurus,
If you confirm the activity later then the latest date of your activity and you reschedule then the system moves all the activities backwards.
Example
Act 1 -> act 2 -> act 3 -> act 4
16/08 17/08 23/08 30/08 = latest date
You confirm act 2 on the 24/08 instead of 17/08. You reschedule then the system postpone act 3 and act 4 with 1 week.
We want that the system doesnu2019t touch the dates of activity 3 and 4.
what are settings needs to be done to achieve this?
Regards,
AHS.
solved by removing tick propose dates in confirmation parameter
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, Just check tcode OPU6 and there is an option "Shift Order". Select this check box and see if that resolve the issue.
rgds,
Abhinay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For partial confirmed activities, you can achieve your requirement by shift order function, for details read SAP Help.
For fully confirmed activities, actual dates will be considered during rescheduling. If you dont want the system to change the successor activities dates, then simply dont reschedule your project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.