PO created but Status showing as Awaiting for approval in extended classic

Former Member
0 Kudos

Hi Experts,

SRM 5.0 extended classic scenario,SC approved and PO created but status showing in follow on documents node in SC as awiting for approval.

Can any help in finding solution.Thanks in advance.

Thanks,

Babu

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Masa,

Issue resolved.Purchse order strucked up,so I have started manually through T- code:SWUE - Create event.

Thanks a lot for your cooperation.

Thanks,

Babu

Former Member
0 Kudos

Hi Babu,

I am facing the same issue in the ECS SRM 5.0 after approving the shopping cart the PO created in EBP but the WF status is waiting and PO is not transmitted to R/3. Below is the status of SC and PO in BB_PD. Kindly suggest what could  be the problem where i can analyze.

SC

                    Status         Description                    Inactiv

HEADER     I1015          Awaiting Approval              X

HEADER     I1021          Created

HEADER     I1038          Complete

HEADER     I1106          Shopping cart ordered

HEADER     I1129          Approved

0000000001 I1111          Item in Transfer Process       X

0000000001 I1113          Follow-on Document Created

0000000002 I1111          Item in Transfer Process       X

0000000002 I1113          Follow-on Document Created

PO

Stats:

           Status         Description                    Inactiv

HEADER     I1015          Awaiting Approval

HEADER     I1021          Created

HEADER     I1038          Complete

HEADER     I1180          Document Completed

Thanks,

Kannan B

Former Member
0 Kudos

Hi Masa,

Thanks you very much for quick reply.

Both PO and SC in BBP_PD looking completed status,but in extended classic scenario it is showing Awiting for approval after PO create even no workflow found for PO.

How can I found why the status showing Awiting for approval in monitor shopping cart.

Please help to resolve the issue.

Thanks,

Babu

9654942305

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

Please clarify the document status and workflow status in BBP_PD transaction like this. It is not clear.

SC:

Document Status: Completed

Workflow Status: Completed

HEADER I1015 Awaiting Approval X

HEADER I1021 Created

HEADER I1038 Complete

HEADER I1106 Shopping cart ordered

HEADER I1129 Approved

0000000001 I1111 Item in Transfer Process X

0000000001 I1113 Follow-on Document Created

PO:

Document Status: Completed

Workflow Status: Completed

HEADER I1009 Held X

HEADER I1015 Awaiting Approval X

HEADER I1021 Created

HEADER I1038 Complete

HEADER I1039 Incomplete X

HEADER I1043 Ordered

HEADER I1080 In Transfer to Execution Syst.

HEADER I1180 Document Completed

Regards,

Masa

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

What is the document status for SC and PO in BBP_PD transaction?

Regards,

Masa