Former Member
0 Kudos

Is there any link which tells how to read BOP result?

BOP result is showing date and quantity status as "no confirmation (red coulored circle) for one of the sales orders. but in r3, this order is getting confirmed in later dates.

example- requirede date was 09.08.2010 and quantity was 270

its getting confirmed at 2 other schedule lines- on 22nd with 108 quantity and on 27th with rest of the 162 quantity.

i am wondering why error sign is shown (red) why not warning if it is not getting confirmend on requested date?

Can anyone help me with this??

Thanks in advance!!

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi ,

Execute /SAPAPO/BOP_RESULT trascation with your variant details.

Inside the transaction please use 'I' (Information) button on the right most corner to find information about BOP result options.

And when there is a confirmation at later date it always shows it as two different lines.If you expand the + symbol on the Sales order & item ...which has RED , it shows the RDD (Requeste dDelivery Date).

In the next line , Sales order & schedulelines , it will show as calendar symbol (date proposal) and confirmation for quantity.

Please place cursor on each & every symbol (even on signal symbols ) on the result grid to get to know the result.

Best Regards,

Deepthi

Former Member
0 Kudos

Thanks both!!

pavan_verma2
Contributor
0 Kudos

Hi,

When you are in T code /SAPAPO/BOP_RESULT - Backorder Processing Result

You have to select " X Original Requirements/ Confirmation situation" .

Thanks,

Pavan Verma