Hello all,
this is our current setup. Sales order (VA01) is created with reference to a quotation (VA21). Date between the two are different, meaning quotation can be created today, and SO is created 2 months from now.
Proposed pricing date in sales document header is set to blank (Proposal based on today's date)
I have made changes in routine 101 to change the pricing date to the current SO date however when i try to create an SO, the currency still reflects the rate of the quotation.
I tried to clear the field VBKD-KURSK (doc currency rate), it does not automatically redetermine in SO creation despite having the correct pricing procedure date.
Anyone got inputs?
Can you check the copy control settings in t.code VTAA.
At item level, try to change the pricing type as C - Copy manual pricing elements and redetermine the others and test.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Edward
There could be some config avenues but nothing comes to my mind. I think you need to work with the currency translation date- VBKD-KURSK_DAT. You need to make that equal to pricing date I suppose.
There is a OSS note on a similar subject - when you are creating a sales order with a BAPI- and you may borrow the concept from there.
1367075 - Conversion date is not adjusted (KURSK_DAT)
Hope this helps. Let me know.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.