Hello guys,

I have a situation here

I configured tolerance limits tr.groups 01-09 / act 3/ usage 100

So i expect that purchase requisition will not consumpt my budget.

so :

budget 5 mln

purch.reqA 1mln

purch.reqB 4mln

purchase order 245k

AND another purchase order is not allowed to be posted due to AVAC .

Why AVAC works if tolerance limits have excluded purch.requisition ?

Thanks !

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

I don't. I want PR not to eat the budget. Only PO can do it.

Former Member
0 Kudos

In that case please check if the note 955107 is implemented in your system. If it is not implemented please implement the note and PR commitment will not be taken into account during AVAC.

Answers (2)

Answers (2)

Former Member
0 Kudos

ok ok , i got it , sorry. Will try to do that. Thanks

Former Member
0 Kudos

Hi,

If you do not want purchase requisition commitment to be taken into account during availability control please check the note 955107.

This might help you.

Best Regards,