Hello guys,
I have a situation here
I configured tolerance limits tr.groups 01-09 / act 3/ usage 100
So i expect that purchase requisition will not consumpt my budget.
so :
budget 5 mln
purch.reqA 1mln
purch.reqB 4mln
purchase order 245k
AND another purchase order is not allowed to be posted due to AVAC .
Why AVAC works if tolerance limits have excluded purch.requisition ?
Thanks !
I don't. I want PR not to eat the budget. Only PO can do it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ok ok , i got it , sorry. Will try to do that. Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you do not want purchase requisition commitment to be taken into account during availability control please check the note 955107.
This might help you.
Best Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.